Synopsis of bridge scores

  • α squad score: 3.89 * 10 ^ -6
  • Ω squad score: 2.10 * 10 ^ -6
  • Current best team score: 1.9747 * 10 ^ -6

Team members

Dan Cabrera Matt Bowers Tony Blekicki Frank Chien David D'Annunzio

Report

Design Process

We based our designs off of our common knowledge of bridges. The general agreement was that cutting out triangles would create the strongest bridge. Our final team design came from playing around with different dimensions of the cut out triangles and seeing which combinations worked the best. After achieving a good score, we decided to eliminate the corners from the triangles because stress builds up at the corners. We rounded out the inside points of our triangles, which further increased our score.

Reflection

Looking back, we had a strong bridge design. However, our design was geared more towards having the force applied to the bottom of the bridge. Most bridges are not designed to have the weight directly on top, which was what this project was about. Since our bridge was designed around existing bridges, we didn't approach the problem in the best way possible. If the weight had been distributed along the bottom of the bridge, we think we would have received a higher score.

← Back to Bridge Section project page ←